Before starting the process, remember to have the following documents/information to hand. You also have all the OTV technical information available.

Documents for:

Standard procedure

 

Authorisation from the installation’s owner
See the standard authorization document

Receipt acknowledging presentation of the guarantee

Approval of presentation of the guarantee

  CUPS

DNI Powers

  Preliminary Plan

Application for scope of ordinary Environmental Impact Assessment (EIA) / application for start of EIA
Notes:

  1. If your facility does not need this document, please provide us with a signed letter (by a representative with powers of attorney) in which you indicate that your facility does not need to go through the environmental impact statement process.
  2. If you have not yet applied, please provide us with a signed letter (by a representative with powers of attorney) indicating that you have not yet applied.

Necessary documents for the acceptability procedure with the System Operator (REE) Check the required documents

 Agreement between owners
See the standard document of agreement between owners

Documents for:

Fast-track procedure
(Low Voltage P<=15 kW)

Applications for <15kW power, involving an urban area and surplus generation, must be through the fast-track procedure.

Annex II of RD 1699/2011. Proposed connection point

Technical report/description of the installation

Authorisation from the owner
See the standard authorization document

 Agreement between owners
See the standard document of agreement between owners

Note: If you have any queries about deadlines for your application, you can check them in the Current legislation section, in New generation connection.

Remember that…

The data in your application must match the data in the documents attached