Facilities that are connected to our UFD, S.A. electricity grid must meet a series of technical specifications which are set out in the following regulations.

Particular specifications

PDF icon

Technical requirements to connect high-voltage installations of Un > 36 kV

The document specifies the technical requirements to be met by installations to be connected to High Voltage networks of Un > 36 kV as well as other parts of the connection installation that for reasons of safety, reliability and service quality must meet the aforesaid conditions (document available in Spanish).

PDF icon

Technical requirements to connect high-voltage installations of Un ≤ 36 kV

The document specifies the technical requirements to be met by installations to be connected to High Voltage networks of Un ≤ 36 kV as well as other parts of the connection installation that for reasons of safety, reliability and service quality must meet the aforesaid conditions (document available in Spanish).

PDF icon

Particular Specifications for Connection Installations. Low Voltage Connection Installations

The document defines and regulates the technical characteristics to be met by new Low Voltage connection installations to be connected to the distribution network (document available in Spanish).

PDF icon

Particular Specifications for Connection Installations. Generators connected to Low Voltage networks

The document defines the technical conditions and characteristics required to connect generators to the Low Voltage network (document available in Spanish).

Royal Decree 1663/2000 has been revoked by the single repealing provision of Royal Decree 1699/2011, of 18 November, published in the BOE of 8 December 2011.

PDF icon

Particular Specifications for Connection Installations. Lines connected to High Voltage networks of Un > 20 kV

The document specifies the conditions and characteristics to be met by new network extension electricity lines connected to High Voltage networks of Un > 20 kV and for other parts of the connection installation that for reasons of safety, reliability and service quality are required to meet the aforesaid conditions (document available in Spanish).

PDF icon

Particular Specifications. Technical Requirements for the Construction of Substations connected to High Voltage networks of Un > 36 kV

The document specifies the conditions and characteristics to be met by new network extension electricity substations connected to High Voltage networks of Un > 36 kV (document available in Spanish).

PDF icon

Technical requirements for Energy Measurement in High Voltage networks of Un ≤ 36kV.

This document establishes the technical conditions that must be met by power measurement installations for billing and supply settlement, as well as electricity producers connected to UFD’s high voltage distribution networks of Un ≤ 36kV, including self-consumption installations, provided that the measurement point is not located inside an electrical substation. (Document available in Spanish).

PDF icon

Technical Requirements for Energy Measurement in Low Voltage Networks

This document establishes the technical conditions that must be met by power measurement installations for billing and supply settlement, as well as electricity producers connected to UFD’s low voltage distribution networks, including self-consumption installations. (Document available in Spanish).

PDF icon

Technical Requirements for Energy Measurement in High Voltage Networks of Un > 1 kV in electrical substations.

The document defines and regulates the technical characteristics to be met by new Low Voltage connection installations to be connected to the distribution network (document available in Spanish).

PDF icon

Particular Specifications for Connection Installations. Carrying out Measurements and Tests on Underground Lines before rolling out

The purpose of this document is to establish the technical requirements for carrying out measurements and tests on underground lines. The aim is to guarantee a level of reliability and a quality that ensures they operate correctly in the distribution network (document available in Spanish).

PDF icon

Low Voltage Overhead Power Line Project

The document establishes and justifies all the construction data that enables the undertaking of projects and the subsequent construction of Low Voltage Overhead Power Lines, as provided for in current norms and regulations and in compliance with the company’s standards (document available in Spanish).

PDF icon

Overhead Power Line Projects up to 20kV

The document establishes and justifies all the construction data that enables the undertaking of projects and the subsequent construction of High Voltage Overhead Power Lines of Un <= 20 kV, as provided for in current norms and regulations and in compliance with the company’s standards (document available in Spanish).

PDF icon

Low Voltage Underground Power Line Project

The document establishes and justifies all the construction data that enables the undertaking of projects and the subsequent construction of Low Voltage Underground Power Lines, as provided for in current norms and regulations and in compliance with the company’s standards (document available in Spanish).

PDF icon

Underground Power Line Projects up to 20kV

The document establishes and justifies all the construction data that enables the undertaking of projects and the subsequent construction of High Voltage Underground Power Lines of Un <= 20 kV, as provided for in current norms and regulations and in compliance with the company’s standards (document available in Spanish).

PDF icon

Project for the construction of Outdoor Stations

The document establishes and justifies all the construction data that enables the undertaking of projects and the subsequent construction of Outdoor Distribution Transformer Stations, as provided for in current norms and regulations and in compliance with the company’s standards (document available in Spanish).

Consulta el documento*

*Este documento está en proceso de actualización, se adjuntan nuevos planos con detalle de la nueva solución constructiva.

PDF icon

Project for the construction of Transformer Stations in prefabricated and non-prefabricated enclosures

The document establishes and justifies all the construction data that enables the undertaking of projects and the subsequent construction of Distribution Transformer Stations in a prefabricated and non-prefabricated enclosure, as provided for in current norms and regulations and in compliance with the company’s standards (document available in Spanish).

PDF icon

Project for the construction of distribution stations in prefabricated and non-prefabricated enclosures

The document establishes and justifies all the construction data that enables the undertaking of projects and the subsequent construction of Distribution Stations in a prefabricated and non-prefabricated enclosure, as provided for in current norms and regulations and in compliance with the company’s standards (document available in Spanish).

PDF icon

Technical Requirements for Connection of Low Voltage Electric Vehicle Charging Infrastructures

The main objective of this TI is to clarify all aspects (necessary enclosures, connection diagrams, load forecasts, necessary pre-installations, etc.) of ITC-BT 52 and other legislation affecting this type of infrastructure and to establish the criteria for connection to the LV network of UFD.