Connection request

2

Necessary information

  • When we validate the documentation, we will assess the request, taking account of the features of your installation.
  • We will communicate the result of the assessment.
  • If the installation meets the conditions established by current legislation, REE must confirm access to the transport network

3

Technical and financial conditions

  • We need you to accept the communicated access and connection point.
  • We will request the detailed project of your installation.
  • We will tell you when the project and technical and financial conditions are approved.
  • You can make the payment.
  • We will start carrying out the works.

4

We connect you

  • When the works are completed, we will review the measurement installation and give you the Universal Supply Point Code.
  • Contact the supply company you choose and sign the auxiliary services contract. You can find a list of supply companies at www.cnmc.es