Before starting the process, remember to have the following documents/information to hand. You also have all the OTV technical information available.
Documents for:
Standard procedure
Authorisation from the installation’s owner
See the standard authorization document
Receipt acknowledging presentation of the guarantee
Approval of presentation of the guarantee
CUPS
DNI Powers
Preliminary Plan
See the standard technical report for self-consumption installations with installed power up to 100 kW
Application for scope of ordinary Environmental Impact Assessment (EIA) / application for start of EIA
Notes:
- If your facility does not need this document, please provide us with a signed letter (by a representative with powers of attorney) in which you indicate that your facility does not need to go through the environmental impact statement process.
- If you have not yet applied, please provide us with a signed letter (by a representative with powers of attorney) indicating that you have not yet applied.
Necessary documents for the acceptability procedure with the System Operator (REE) Check the required documents
Agreement between owners
See the standard document of agreement between owners
Documents for:
Fast-track procedure
(Low Voltage P<=15 kW)
Applications for <15kW power, involving an urban area and surplus generation, must be through the fast-track procedure.
Technical report/description of the installation
See the standard authorization document
Authorisation from the owner
See the standard technical report for self-consumption installations with installed power up to 100 kW
Agreement between owners
See the standard document of agreement between owners
Note: If you have any queries about deadlines for your application, you can check them in the Current legislation section, in New generation connection.